A Reno Tale

Two years in the planning and we have FINALLY started.

Translate

Sunday, February 27, 2011

Congratulations, Gabe!!!


Week 18

The bay window looks like it belongs now. 

Week 18

Will has called for an engineers inspection, then the city inspection and then on to the insulation, then drywall. Getting close!
Have to start thinking about getting out of here for the drywall, which is still slated for next week.  I have a friend who is off to warmer places for 3 weeks and I will be house sitting along with Lulu.  Perfect timing.
No plumbers all week, as they are waiting for our shower and tub rough-ins which have been on order.  They arrived at the end of this week so that will be taken care of next week.
Will and Gabe have kept busy with finishing up the bay window and some strapping in Linda's room for the plumbing that extends below the floor joists.


Week 18

Gabe got his fireman job !! He has been in and out getting things sorted out for that. Very exciting for him, but my house isn't finished!  Haha, Will assures me that he has built many houses without Gabe.
The construction heater that I have been using in my room has gone on the fritz, and I pretty much have had no heat for about 4 days. It is February and still COLD!  Grrrr.  Turns out the trouble wasn't with the heater but the breaker.  Anna replaced it and now I have lovely heat blasting, thank you.
We passed an electrical inspection for my floor this week and Anna has some of the potlights going upstairs and she is working on the roughin on Linda's floor. 