A Reno Tale

Two years in the planning and we have FINALLY started.

Translate

Monday, May 21, 2012

Week 75

April 1 - April 7, 2012
So what do you think? Going to have to go with the expert, Steve, the arborist (arboriculturist), but the shape is odd. Since the centre of the tree is bare, he didn't prune the sides as it would look even stranger.  Will fill out apparently. Another 'we will see'.

Week 75

April 1 - April 7, 2012
On recommendation, a fellow named Steve is tackling the project.  With I might add, several disparaging remarks about holly trees in the process.




Week 75

April 1 - April 7, 2012
So many things to do.  Inside and out.  This is a holly at the back end of the yard that is in desperate need of pruning. Need to get that taken care of before the birdies settle in.

Week 75

April 1 - April 7, 2012
Not sure what I have done wrong now.

Week 75

April 1 - April 7, 2012
I apologize for the dates of the postings and the events being out of whack.  I will be caught soon and things will be put alright.
Anna came by on a Sunday to finish what she had started this week. She completed the under cabinet lighting on my floor, however the pucks are deeper than the predrilled holes so that will need to be redone at some point. There are other things I feel should be done, but they are focusing on closing the permit, so not sure when it will all get done. The number of pot lights in the basement aren't what we had asked for, more need to be installed,  there is no power in the garage, an outlet outside needs to powered up, the gas insert on the main floor, etc. The baseboard heater on my floor is still not working, so it looks like that will need to be replaced.  For now, it is up to us.  The door bell needs to be installed and the under cabinet lighting on the main, which Linda is taking care of. 

Week 74

March 25 - March 31, 2012
Anna, the electrician came by this week to finish up a few things in order to get the electrical inspection rolling.  The pot lights in the basement needed to be reinstalled due to failing the structural inspection way back when.  They were removed to add more floor joists in the rec room area. Here she is installing the fan in the basement bathroom.  Heater still needs to be installed there and the front entrance way on the main. One of the electrical baseboard heaters on my floor has not worked properly since it was installed.  She has installed a new thermostat so we will see.

Week 70 - 73

Feb 26 - March 24, 2012
No pics no updates nada